With a total investment of 126.2 billion yuan, this coal chemical project under construction will resume work



Recently,itwaslearnedfromtheofficialwebsiteoftheYulinMunicipalPeople’s Government that since 2021, Yulin City has insisted on “compensating the two high-rise projects w…

Recently,itwaslearnedfromtheofficialwebsiteoftheYulinMunicipalPeople’s Government that since 2021, Yulin City has insisted on “compensating the two high-rise projects with non-two high-rise projects, supplementing industrial projects with infrastructure projects, and leveraging government investment. In line with the idea of ​​”social investment”, we went all out to seize projects and took multiple measures to stabilize investment. The decline in fixed asset investment in the first three quarters narrowed by 1.6 percentage points compared with January to August, achieving a stop of decline and recovery.

First, optimize the mechanism and consolidate responsibilities. Establish a project promotion mechanism of “scheduling once a week, advancing once a month, and assessing once a quarter”, and arranges the Municipal Development and Reform Commission to go down to supervise counties and districts where fixed investment is declining and special bond disbursement is lagging behind. The municipal government holds key project promotion meetings in different districts to conduct communication at all levels. Compact and compact, forming a joint effort to stabilize investment.

The second is to implement targeted policies and promote projects. Actively seek support from the central province for energy-using projects that comply with national regulations, and strive to resume work on the 50,000-ton degradable plastic projects of Shaanxi Coal Yulin Chemical and Shenhua in November. Speed ​​up the preliminary procedures for projects that have not yet started, and strive to increase investment by 3 billion yuan within the year. Implement weekly scheduling for key municipal projects under construction, and prepare to hold on-site observation meetings for key projects in the fourth quarter to observe and promote implementation.

The third is strong financial support. In the fourth quarter, the city level allocated 4 billion yuan for urban renewal and major infrastructure construction, and the city and county levels added 10 billion yuan of unplanned government investment throughout the year. The city-level funds of 30 million yuan were cashed in as awards, and more than 16.5 billion yuan of investment in industrial technological transformation was completed throughout the year. At the same time, real estate investment will be increased, and 11,000 talent apartments, logistics bases and affordable rental housing will be launched this year and next to stimulate investment while stabilizing housing prices.

In early July this year, the Shaanxi Coal Yulin Chemical Project was temporarily suspended.

Shaanxi Coal Group Yulin Chemical Company The demonstration project of coal quality utilization to produce new chemical materials is currently the largest coal chemical project under construction in the world. The project covers a total area of ​​about 13 square kilometers, with a total planned investment of about 126.2 billion yuan, and an annual conversion of about 24 million tons of coal, including a total of 27 The process equipment and supporting public works mainly include 15 million tons of medium and low-temperature pyrolysis of coal, 5.6 million tons of methanol, 1.8 million tons of ethylene glycol, 2 million tons of olefins and downstream products using these as intermediate raw materials.

Among them, the first phase of the project has a 1.8 million tons/year ethylene glycol project, covering an area of ​​about 4.4 million square meters, and the total project investment is estimated to be about 26.5 billion yuan. It is also currently The world’s largest coal-to-ethylene glycol unit under construction is scheduled to be mechanically completed in June 2021;

The first and second phases are to build 5.6 million tons/year methanol, 2 million tons/year olefins and deep processing projects , is planned to be completed by the end of 2023.

The second phase of the project is led by coal pyrolysis and is also divided into two phases. The first phase is an industrial demonstration device for 1.2 million tons/year pulverized coal pyrolysis and 500,000 tons/year coal tar deep processing. The machinery is planned to be completed in June 2021;

The second phase will expand the pyrolysis scale to 15 million tons, and extend the coal tar industry chain to produce aromatic hydrocarbons and aromatic olefin-combined downstream products, which is planned to be launched in 2022 Construction will begin and all construction content will be completed by the end of 2025.

It is understood that Hualu Technology has undertaken the EPCO general contracting of the sewage treatment unit, the EPC general contracting of the purification unit, and the EPC general contracting of the air separation unit of the Shaanxi Coal Yulin Chemical Ethylene Glycol Project, with a total winning bid of more than 3.5 billion yuan. . </p